Levels and Models (covered in ANSI A250.8 (SDI 100) "Recommended Specifications for Standard Steel Doors and Frames") are SDI term aid in the selection and specification pr...
Raceway availability: Optional factory installed raceways are available in doors but are not available in frames. Preparation Info: Steelcraft installs a flexible 1/2" ID steel conduit through the...
The 4040SE is non handed and can be mounted on the push or pull side of the door.
The three most common steel types are cold rolled steel, galvannealed steel, and galvanized steel. Cold Rolled Steel (CRS) is suitable for most interior applications, is uncoated steel a...
Hinge backset is the dimension from the leading edge of the hinge to either the stop on the frame or to the stop face (push side) of the door. For operating clearance, the hinge backset on the d...
Tornado shelter applications require the use of Paladin PW14-Series doors and FP14-Series frames: Tornado shelter doors are a tested system comprising of the door, frame and hardware. ...
Astragals are required on: 3 hour fire rated pairs: Double doors - swinging in the same direction Double Egress - swinging in opposite directions Fire rated Dutch Doors Fire rated 1 3/4" t...
Steelcraft have tested different types of doors and frame assemblies using Zero International gasket seals for the various STC ratings. Tests are in accordance to ASTM...
Frames can be installed either KD (knock down) or welded to receive the STC rating.
Steelcraft borrowed light frames are not listed/tested. Check with the glass manufacture if they are listed and with what type of framing used.
Sound seals are required. Zero International Gasket Notes: Perimeter Seals – Zero #475 applies to the stop of the head and jambs. Door bottom – Zero #367, surface applied. Threshold ...
When rust appears, repair the affected surfaces by finish smooth, clean, treat for maximum paint adhesion, and touch up the surfaces with a direct to metal (DTM), rust inhibitive primer.
Prime or painted surfaces which have been scratched or otherwise marred during installation (including field welding) and/or cleaning must be field repaired and re-primed by the installing contractor.