EPT frame prep measurements

RELATED FAQS

Question
Answer
Yes, a filler plate can be used to cover an EPT prep as long as it is made from the same material as the frame. This information can also be found in NFPA 80 under Chapter 5 for Field Modifications.
EPT installation guidelines are as follows: Recommended location is 6" below top hinge per template Steelcraft will locate the power transfer prep at the Von Duprin recommended template locati...
The Locknetics 9100 series electric strikes are replaced with Von Duprin 6211 and 6210 electric strikes.   The 6211 is used if the frame is being replaced. The 6210 is for ...
The minimum rose that can be used on the 61L (ANSI/BHMA A156.115.18) preparation is 3 7/16". Steelcraft's 61L lock prep (often referred to as the "Squashed Turtle lock prep") is designed for Bored...
On May 1, 2013 the LM9000 lock was discontinued and replaced with the LM9300 Multipoint Lock. 
The Schlage LM9000 series lock was originally designed for use in FEMA (tornado) storm shelter openings and/or Florida Building code (hurricane) assemblies.  Doors, frames and hardware can be order...
  Specify either an L or B doors for use with the LM9000 or LMV9000 Specify the F frame for use with the LM9000 or LMV9000 Order the lock from Schlage as you would normally The concealed rods...
Raceway availability: Optional factory installed raceways are available in doors but are not available in frames. Preparation Info: Steelcraft installs a flexible 1/2" ID steel conduit through the...
The backset is 2 3/4" from edge of door to the center line of the device and strike. The preparation for the WS98/99 strike must be specified when placing order for the frame.
Electrical hinges or a power transfer units are the most commonly used practices to run electric power to locks and/or strikes. Electric Hinges: Most electric hinges will fit into a standard 4 ...