fire rated frame with sidelight

RELATED FAQS

Question
Answer
On fire rated transom and/or sidelight frames and fire rated window frames, Steelcraft labeling procedures only control the O/A width and/or height of the frames based on wall condition. The amount...
Elevation frames are available in: F-Series (F16 or F14) FN-Series (FN16 or FN14) MU-Series (MU16, MU14) Additional parameters of the frame components: Perimeter (Head and Jambs) Frame: ...
No. Fire rated double egress frames must be a stand alone 3 sided frame assembly. If transom lights and/or sidelights are required, they must be built and installed as separate Fire Window assemb...
Maximum hourly rating for a transom and side light or panel frame is 1 1/2 hour (90 minutes). In masonry wall application the maximum is 13'6" x 12'2" In stud wall application the maximum is 13...
Yes, wood doors can be used and installed in most hollow metal frame applications including FE-Series and DE-Series Double Egress frames. Caution - For fire rated applications the wood door manufa...
Transom panels are available in the following constructions: 1 3/4" thick panels with interior construction similar to an L-Series door installed into a frame either Without a transom bar - r...
Yes, a filler plate can be used to cover an EPT prep as long as it is made from the same material as the frame. This information can also be found in NFPA 80 under Chapter 5 for Field Modifications.
F-Series frames are available without returns: Fire Rated frames must have welded corners. Frames must include weled in wood or steel stud anchors. Installation requirements: Frames must be...
Grouting frames is: A process done in the field during hollow metal frame installation  The internal cavity of the frame is fill with masonry or mortar It is intended to mainly provide ...
Yes, hospital stops are available on fire rated frames. Maximum approval = 3 hour Maximum sizes:  singles up to 4'0" x 8'0" pairs up to 8'0" x 8'0" Maximum hospital stop height 6" from bot...